The minimum sizes which may be used
1 percent.  At the intersection of the
for
TO
construction
are
4-inch
1-percent line and the 8-inch diameter
diameter pipe for a house connection
line, a line is drawn parallel to the
and 6-inch diameter pipe for any other
velocity  lines.
The  new  line  lies
sewer.
between the line of 3 feet per second
and 3.5 feet per second.  Its value is
16. ACTUAL VELOCITY
3.2 feet per second.
The acceptable limits for the sewage
c. Discharge ratio.
The discharge
velocity are 2 feet per second to 10
ratio  is  the  ratio  of  the  actual
feet  per  second.
Velocities  lower
discharge  (flow)  (QA)  to  the  full
than this will tend to deposit solids
discharge  (Qc).
Thus  the  discharge
in  the  sewer  and  velocities  higher
ratio is found by dividing the actual
will  scour  out  the  invert  of  the
flow  by  the  full  flow.
For  the
sewer.
Occasionally  a  choice  is
example started above the actual flow
forced upon the designer of using a
is 300 gallons per minute and the full
lower velocity than 2 feet per second
flow
is
500
gallons
per
minute.
or  of  putting  in  an  automatic  lift
Therefore the discharge ratio is
station.  If it can be shown that the
costs  incurred  in  keeping  the  sewer
d. Velocity  ratio.
The  velocity
clean, and perhaps replacing it, are
ratio  is  the  ratio  of  the  actual
cheaper over the design life of the
velocity (Va) to the velocity at full
system
than
the
procurement
and
flow (Vc).  Since Va is not known yet
maintenance cost of the lift station
this cannot be found by division.  The
or  other  special  facility,  then  the
velocity  ratio  is  found  by  use  of
actual  velocity  may  be  decreased  to
figure  15.
The  chart  is  used  by
1.5  feet  per  second  at  peak  flow.
entering along the top or bottom at
There are five steps to finding actual
the  value  of  the  discharge  ratio.
velocity.
Move  vertically  along  the  discharge
ratio value until the discharge curve
a. Full flow.  The full capacity of
is intersected.
From this point move
the  sewer  is  found  by  entering  the
horizontally  to  the  right  until  the
chart at the given slope and moving
velocity  curve  is  intersected.
At
all  the  way  up  to  the  chosen  pipe
this point move vertically up or down
size.
Moving  horizontally  to  the
and read the velocity ratio at the top
right
from
this
point
the
full
or
the
bottom
of
the
chart.
capacity can be read.
Continuing the
Continuing the example, the chart is
example  started  above,  the  chart  is
entered along the bottom at the value
entered at the 1-percent slope line.
of discharge ratio 0.6.
Moving up to
Moving  up  to  the  8-inch  line  and
the  discharge  curve,  across  to  the
reading to the right, a full flow of
velocity
curve,
and
down
to
the
500 gallons per minute is obtained.
bottom,  a  value  of  1.045  is  read.
Thus the velocity ratio is 1.045.  The
b. Velocity  at  full  flow.
The
only case where this method of using
velocity at full capacity is found by
figure 15 gives an incorrect answer is
entering  the  chart  at  the  design
when  the  discharge  ratio  is  1.0.
slope.
Move up vertically until the
However,  when  this  is  the  case  the
design
pipe
size
is
intersected.
actual velocity must be equal to the
(This  point  of  intersection  is  the
full flow velocity because the pipe is
same point found in a above.)  Through
flowing  full.
Since  the  velocities
this point draw a line parallel to the
must be equal, the velocity ratio is
velocity lines.
Knowing the velocity
1.
value of the line above and below, an
estimate of the velocity value of the
e. Actual
velocity.
The
new line can be made.
This is the
velocity
ratio
is
the
actual
velocity  at  full  flow.
For  the
velocity
divided
by
the
full
example above, the chart is entered at
4-20