SELF TEST
Note:
The following exercises comprise a self test. The figures following each question refer to a paragraph
containing information related to the question. Write your answer in the space provided below each
question. When you have finished answering all the questions of this lesson, compare your answers with
those given for this lesson in the back of this booklet. Review the lesson as necessary. Do not send in your
solutions to these review exercises.
Estimating is one of the most important steps in planning a construction project. In what way does good
1.
estimating help insure successful completion of a project? (Para 4-1a)
What is the first step an estimator should take when assigned to a new project? (Para 4-1b(1))
2.
Where does the estimator obtain the information he needs to prepare the bill of materials? (Para 4-1b(3))
3.
Plans and specifications for bridges, buildings, and other vertical structures normally contain bills of
4.
materials. What is the function of the material estimator if alterations or modifications of the plans are
necessary? (Para 4-3a)
List the five essential elements of any bill of materials. (Para 4-4a)
5.
In reference to the preparation of a takeoff list, what is the meaning of the rule "keep it separate?" (Para 4-
6.
5b(1))
When the materials estimator converts the actual requirements for a certain size of lumber into the number of
7.
pieces of standard lengths to be procured, what is his primary consideration? (Para 4-5b(3))
4-13