LESSON 2
PRACTICE EXERCISE
ANSWER KEY AND FEEDBACK
Item
Correct Answer and Feed Back
1.
A.
Stretcher
(page 2-3, para 2-5a)
A stretcher block is the ....
2.
C.
To allow for a greater mortar bedding area
(page 2-11, para 2-9)
Be sure to lay all blocks with the thicker ....
3.
A.
Every course
(page 2-20, para 2-20)
The last block to be installed ....
4.
C.
S-Shaped jointer
(page 2-22, para 2-21b)
Use the S-shaped jointer ....
5.
B.
4
(page 2-27, para 2-25)
Anchor bolts should be spaced ....
6.
D.
Beams
(page 2-32, para 2-29a)
Lintel blocks can be used for ....
7.
D.
4
(page 2-20, para 2-20)
When you install the closure block ....
8.
A.
Tie bars
(page 2-23, para 2-23a)
Tie bearing walls together with a tie bar ....
9.
C.
Corner
(page 2-11, para 2-9)
Lay the corner block first ....
10.
D.
Top curse
(page 2-14, part E Intro)
They are usually spaced at ....
11.
C.
3/4
(page 2-15, para 2-14)
When the mortar in the control ....
12
A.
To determine the height of each course
(page 2-18, para 2-17)
You should use a story or course pole ....
2-38
EN5157